Optimising business processes by enhancing MRP and adding MPS functionality
Find out how Toyota Material Handling Manufacturing Italia optimised its operating processes
Subjects involved
Toyota Material Handling Manufacturing Italia (part of Toyota Industries Corporation – TICO, which manufactures warehouse equipment and counterbalanced trucks to the quality standards of the Toyota Production System – TPS) and Sinfo One SpA (a solution provider specialising in business management solutions, management and organisational consulting, etc.).
Benefits
Phase 1: After the initial study aimed at process optimisation, the implementation of Oracle JD Edwards EnterpriseOne began.
Phase 2: A constraint was set to make the most of JDE standard functionality in order to optimise timing, costs and risk management.
Phase 3: Where it was not possible to stick to the standard, the aim was to implement a solution that could truly provide leverage for TMHMI’s day-to-day work.

The Challenge
Toyota Material Handling Manufacturing Italia – part of Toyota Industries Corporation (TICO) – is a European company with plants in Sweden (Mjölby), France (Ancenis) and Italy (Bologna), offering a wide range of warehouse equipment and counterbalanced trucks manufactured to the quality standards of the Toyota Production System (TPS). Over 95% of truck production takes place in Europe. The products – known for their high quality – are sold under the TOYOTA, BT and CESAB brands.
The challenge was to meet the following objectives:
- design a new production support system and a new way of working in harmony with TPS (Toyota Production System);
- harmonise factory processes to optimise time, costs and risks;
- review processes from a digital transformation perspective: the TPS smart factory had to be complemented by smart work;
- support TMHMI’s new sales philosophy: not only product quality but also the quality of customer service and, more generally, of the customer experience.
The Solution
The analytical approach adopted, taking the required objectives into account:
- After the initial study aimed at process optimisation, the implementation of Oracle JD Edwards EnterpriseOne began;
- The constraint of making the most of JDE standard functionality was met, in order to optimise timing, costs and risk management;
- Where it was not possible to stick to the standard, the aim was to implement a solution that could truly provide leverage for the day-to-day work of Toyota Material Handling Manufacturing Italia (TMHMI).
Process optimisation resulting from the implemented solution
- Interaction with suppliers has improved;
- MRP is even more powerful and complete, and the customisations have added MPS functionality without purchasing specific modules.
A phased costing model (estimate, engineering and final costing) has been implemented for customisation requests via the portal, integrated with a cost variance analysis tool.
In detail, MRP has been shaped around the specific requirements of KANBAN and Junjo messaging, which governs the delicate mechanism of external supplies delivered directly to the assembly lines.
Toyota Material Handling Manufacturing Italia (TMHMI) now has smarter, automated planning and production that adapts better to requests and mistakes. The number of people involved in daily planning has been reduced, allowing resources to be moved to higher value-added activities.
An efficient and effective method
At its peak, the project involved some twenty Sinfo One experts and about forty TMHMI “key users”. On average, up to 25 key users worked in the various implementation phases. For the go-live, the “big bang” approach was chosen: on the scheduled date the old system was switched off and JD Edwards Enterprise One was switched on. Today, about a third of the 570 people working for TMHMI – including white collars and technical staff – have access to the new ERP.
Ecosystem partners involved

Sinfo One
Sinfo One SpA is a systems integrator and partner for the digital transformation of businesses, implementing and integrating…
Parma (PR)